Please read through your offer letter from the DTI carefully. Paragraphs within it relate specifically to the areas below and provide additional information. It will also tell the project team what they are contractually obliged to supply the DTI for grant funding to be paid. Please note, these guidelines are for Full Collaborative Projects only.
   
 

Monthy Report

Quarterly Report

Final Report

Ad hoc Reports


Claims

Reports

Monitoring
Meetings

Forms for
Download

Reporting

Monthly Report

• Monthly Reports are simply to let us know how your project is progressing (in the minimum amount of words).

• Your first Monthly Report is expected one month from the project start date in your offer letter and monthly thereafter.

• You are not required to submit a Monthly Report for the month you submit a Quarterly Report.

• Please email Monthly Reports to support@ictcarrier.co.uk using this form

• The form opens in Word and on completion of project details click on 'File' 'Send to' 'Mail Recipient' 'Send a Copy'.

• Please ensure your Project Ref. and Reporting Period is stated in the title of the email.

• Please let us know of any relevant meetings or additional information.

• Any queries regarding reports should be addressed to ICT Carrier on 01355 27 27 72 or at support@ictcarrier.co.uk


return to top

Quarterly Report

• This formal report can be downloaded here.

• Your Quarterly Reports should be submitted 3 months from the project start date in your offer letter and 3-monthly thereafter, whether or not you are making a claim.

• You are not required to submit a Monthly Report for the month you submit a Quarterly Report.

• Please send your Reports to the DTI as a hard copy with your Interim Claims, and an electronic copy to support@ictcarrier.co.uk

• The quarterly report will show progress against your project plan, highlight issues & concerns and detail any corrective action you to intend to take.

• It will also track your spend profile against your project plan and will highlight future deviances.

• Any queries regarding reports should be addressed to ICT Carrier on 01355 27 27 72 or at support@ictcarrier.co.uk


return to top

Final Report

• The form for this comprehensive report is currently being designed and will be available for download shortly.

• Your Final Report covers the whole term of your project and should be submitted to the DTI with your Final Claim, no later than 6 months from the project completion date in your offer letter, unless other arrangements have been agreed.

• Please send a hard copy to the DTI and an electronic copy to support@ictcarrier.co.uk (preferably in .pdf/adobe format).

• The Final Report will illustrate the work done, mapped against your project plan and will highlight any issues that arose and the corrective action taken.

• It will compare your spend profile against your original project plan, highlighting and explaining any deviances.

• Any queries regarding reports should be addressed to ICT Carrier on 01355 27 27 72 or at support@ictcarrier.co.uk


return to top

Ad hoc Reports

• Should your project deviate significantly from your project plan between Monthly Reports, please email support@ictcarrier.co.uk to inform the Co-ordination Team.